NIBULON - Complex of construction and installation works

Complex of construction and installation works for NIBULON
T200
В М

UKRSTAL CONSTRUCTION completed a sсope of construction and installation works for one of the leaders of the Ukrainian agricultural market - NIBULON

Works were carried out as part of the construction of the modern river transshipment terminal in Dnepropetrovsk region, in the village Maryanskoye of Apostolovsky district.

Our participation in the project included the development of workshop drawings, manufacturing and installation of the following metal structures:

- cable overpass,

- grain storage barn,

- overpasses and galleries,

- suction unit,

- dryers,

- installation of wet grain silos with overpasses

In addition, dry pipes were fabricated and mounted, and profile sheeting of the dryer was made.

Workshop drawings were developed by the design department of UKRSTAL, metal structures were manufactured by “UKRSTAL Dnepr” and “UKRSTAL Zaporozhye” plants, installation was performed by the UkrstalMontazh Construction Company.

For all scope of works the term of 70 calendar days was allocated, so works was carried out in an extremely short time.